Vendor scheduling MVP

What the office does today with every work order, measured on 8,374 of them, and the smallest version of Clara that does it.

Proposed, pending review, Oct 24 2026. Plan only, no build. Written for hand-off to another session. Part of the maintenance hub.

1. Answer first

The handyman hunch holds. 81% of Situs and 67% of Western Slope work orders go first to their own people.1

AppFolio already tells the tech and the vendor, in the same minute as the assignment. Nobody types that text.

The calendar is not the dispatch tool, and the Priority label is unused. The Emergency flag drives speed: done in 0.86 days vs 7.74 for Normal at Situs.

Preferred vendors are real at Situs (one vendor gets 83% of pest jobs, one gets 76% of appliance jobs) and weaker at Western Slope (21% to 64%).

1 Share of the first assignment. Situs 80.7% (66.2% to a tech, 14.2% held by the coordinator). Western Slope 63.0%, or 67.2% counting 223 orders a tech closed with no assignment step.

2. How the office works today

A person routes, AppFolio notifies, the tech does the work. Numbers are Situs / Western Slope.
Report comes in resident portal, call center, staff, AppFolio bot resident waits for a person: median 4.8 h / 12.6 h (staff-made: 0 min) Office coordinator routes it a person, or AppFolio's bot (1,199 / 603 orders) In-house tech 81% / 63 to 67% Outside vendor 19% / 37% AppFolio notifies, automatically tech: auto text, email or call 82.5% / 91.0% vendor: email in the same minute 96% / 98% A time gets set (sometimes) 6.5% / 34.8% of orders ever get one WS: resident picks a window (363 of 628) Work done, order closed median 5.8 / 3.8 days in-house 4.7 / 3.7, vendor 12.9 / 7.0
Not in the picture: the AppFolio calendar. 57 of 2,486 Situs orders from 2026 (2.3%) appear on it, always under the vendor company, never a tech. Western Slope has no on-call calendar enabled.
SitusWestern SlopeSame?
First sent in-house80.7%63.0% (67.2%)Same: mostly own people
Who creates ordersoffice 2,073, bot 1,205, call center 1,204, tech 676tech 606, office 276, bot 174, call center 154Different
Priority "Urgent"2.4%1.2%Same: unused
Days to done, Emergency flag vs Normal0.86 vs 7.74 (n 141 / 3,719)1.94 vs 4.66 (n 53 / 951)Same direction
Gets a scheduled time6.5%34.8%Different
Top vendor's share per category24% to 83%21% to 64%Situs tighter
Make-ready sent to vendors38% (366 of 962)60% (174 of 290)Different
On-callweekly rotation: one person took 90%+ of pages in 78.4% of 88 weeksnot enabledDifferent
Roster churnone tech faded mid-2025, one joined Sep 2025the maintenance manager (468 first assignments) left end of July 2026Same: rules go stale

3. The rules, with hit rates

Trained on the oldest 70% of assigned orders, scored on the newest 30% (Situs 1,724, Western Slope 487).

In-house or vendor? share right

RuleSitusWestern Slope
Always in-house78.9%69.6%
By category78.9%73.1%
Confident rules only84.6%, on 57.2% of orders89.1%, on 26.3%

Confident = 80%+ right on training, 5+ cases. Example: plumbing, HVAC, doors and electrical at Situs stay in-house 90.7% to 95.6%; make-ready at Western Slope goes out 61.9%.

Which person? share right

RuleSitusWestern Slope
Busiest person15.5%16.8%
By category20.5%19.5%
Category + property28.0%22.2%
Confident person rules61.7%, on 8.6%57.1%, on 8.6%
Right answer in top 241.0%54.6%
In-house: same tech as the last order at this property, prior 14 days57.3%, on 95.1% of in-house70.8%, on 72.5%

The office routes by territory, rotation and roster, not by trade. After hours at Situs it is the week's on-call tech.

Preferred vendor per category top vendor's share of vendor orders, of n

CategorySitusWestern Slope
PestDenver Pest Protector 83% of 216Mountain Pest Control 47% of 36
ApplianceUniversal Service 76% of 176Double D Services 64% of 64
HVACCreative Exteriors 29% of 28Activ Construction 58% of 76
WindowsCreative Exteriors 80% of 20Glass Guru 44% of 16
ElectricalCreative Exteriors 47% of 30Bob Davis 55% of 20
Common areaCreative Exteriors 45% of 38Bob Davis 64% of 39
PlumbingUniversal Service 24% of 54Distinctive Design Build 21% of 52
Make-readyA and J Renovation 34% of 304GJ Carpet Cleaning 29% of 183

Universal Service is staff-run (a Situs email address). Creative Exteriors and Bob Davis are each office's general handyman contractor, not specialists.

How long it takes. Situs logs labor on 3,283 orders: median 0.98 h, 90.5% within 4 h. Pest 0.25 h, appliance 0.75 h, plumbing 1.0 h, make-ready 2.5 h. Western Slope logs labor on 3 orders, so durations come from Situs; its most used window is 4 h (185 of 536).

4. What we already have

Most pieces exist. Nothing learns from history, and nothing reads tech availability.
PieceStateReuse?
Pick order: own handyman, then preferred vendor, then specialistliveYes, as the fallback
Preferred vendor roster per trade, building over companylive filled by handYes: the store for learned rules
Text page to the handymanliveOnly where AppFolio does not already text
Vendor quote and dispatch emailstest inbox only no real vendor emailedNot in MVP
Vendor offers times, tenant picksliveYes
Booked visits on the building's Outlook calendarliveYes
Vendor phones or emails a time, it lands on the calendarliveYes
Robot: assign vendor, schedule, change priority, mark doneliveYes: all AppFolio writes
Tech working days, hours, quiet hoursstored, never readYes: read it
"Propose schedule" tooldead invents slotsReplace
February quote parsing and comparisondeleted May 4Later, for bids

AppFolio already does the vendor email, the vendor portal (accept, estimate, schedule, done, invoice), the office and resident notice when a job is scheduled plus a 24 h reminder, and an in-house drag-and-drop calendar these two offices barely use.

5. The MVP

Learn the office's own routing once, assign only when confident, let Clara own the tenant's time and the follow-up.
Report comes in Clara takes it: text, call, portal Learned routing rules from history at onboarding PM confirms once Emergency flag on-call tech now no entry question Confident: assign tech: last at property vendor: preferred Not sure office decides, package ready Clara offers the tenant 2 windows from tech hours + the Outlook calendar tenant picks, Clara confirms Write to AppFolio assignee + schedule, existing robot actions AppFolio notifies tech or vendor unchanged: its text, email, portal Clara closes the loop tenant updates, then "is it done? how was it?"
Purple = Clara's new work. Everything else exists today in our code or in AppFolio.
  1. Learn routing at onboarding. From the customer's own history: in-house or vendor by category, preferred vendor per category, last tech per property, the on-call rotation. Saved into the preferred roster we already have; the PM confirms once.
  2. Assign only when confident. Otherwise the office gets a ready package: the job, the suggested person, the runner-up, the tenant's windows. Expect the confident in-house or vendor call on about 57% of Situs and 26% of Western Slope orders at first.
  3. Schedule. Read tech hours (stored, unread) and the Outlook calendar, offer the tenant 2 windows, confirm, write the assignee and time to AppFolio.
  4. Notify. AppFolio keeps the vendor email and tech text. Clara adds the tenant side and the follow-up after the job.
  5. Emergency. Emergency flag goes to the week's on-call tech, no entry question.

Multiple bids are a later layer. Neither office asks for estimates (0% at Situs, 1.4% at Western Slope) and no order mentions a not-to-exceed amount. The deleted February quote work is the starting point when a customer asks.

Data we do not hold. Western Slope has no tech timers and labor on 3 orders; Situs sets a time on only 6.5% of orders. We hold email subjects, not bodies. Office-to-tech texts happen off AppFolio. A pull would need the coordinators' phone threads, the Situs coordinator mailbox, and AppFolio's per-order sent-email pages.

6. Proof ladder

From the testing playbook. Unit tests are build hygiene, never a rung.
  1. 1Read-only replay of all 8,374 work orders6,398 Situs + 1,976 Western Slope. Hit rate per customer; where rules say "office decides", output byte-identical to today.
  2. 2Willows live runA real tenant text, end to end: windows offered, one picked, AppFolio order with assignee and time, AppFolio's notice, the follow-up. Record ids as evidence.
  3. 3Sandbox companyOne coordinator-led shape (Situs), one manager-in-the-field shape (Western Slope).
  4. 4Supervised week at one customerTurn-on is Fede's call.

7. Open choices

Pick a letter for each.
ChoiceOptionsRecommend
When Clara is unsure
  • A confident only, office gets a package
  • B always assign the best guess
A: even the top 2 guesses are right only 41% / 55%
Who confirms learned vendors
  • A the PM, once at onboarding
  • B Fede
A: they know who left
Who picks the time first
  • A tenant picks from the tech's open windows
  • B tech first, then the tenant
A: Western Slope already works this way (363 of 628)
Make-ready in the MVP
  • A no
  • B yes
A: split per trade, top vendor only 29% to 34%
Who contacts vendors
  • A AppFolio's email and portal
  • B Clara
A: it already reaches 96% / 98% in the same minute