Merge queue and deploy retro

Why GitHub's merge queue failed five times in eleven weeks, why deploys choked once it went off, and the order of work to get stable.

2026-10-01 · times in Central · Proposed — pending review

On this page

  1. The short answer
  2. Getting stable: priorities, in order
  3. Reducing reds: what 90 days of main says
  4. The five attempts
  5. After the queue went off: the choke point moved to deploys
  6. The common cause
  7. The math
  8. Were cross-PR collisions ever the real problem?
  9. What would have to be true
  10. The alternatives
  11. Recommendation
  12. Engineer appendix

1. The short answer

Every attempt broke for a different surface reason, but they all share one cause: we switched the queue on before the PRs going into it reliably passed it. Each time, the queue was the first place some checks ever ran, and we kept changing CI underneath it while it carried the whole team's merges.

A queue multiplies failure. One failed PR throws away the work of every PR stacked behind it. Today about 1 in 7 PRs got kicked out, so the line could clear only about 24–29 PRs an hour. We arrive at about 20–24 an hour. The line grew to 72 and nobody could merge.

Clashes between PRs are real but a minority: about 1 in 6 red-main episodes in the last 30 days. Most red main is machines, tests that never ran on the PR, or one bad PR.

Turning the queue off moved the choke point; it did not remove it. Main went red 4 minutes later and deploys stopped. Same cause: tests that never ran on the PR.

Recommendation (option B): stable first. Queue stays off. Every check that can turn main red runs on the PR. A red main is fixed within 30 minutes by one owner. CI stops changing under the team. Cost and speed come after.

Where the facts come from

GitHub's own change history for the "Require CI" rule (every on/off and setting, to the second), the CI decision log, the CI/CD design page and the "ship in 15 minutes" page, the factory dashboard, the July decision record that retired the first queue, PR bodies, today's standup transcript, the CI lane's session transcripts, and the queue, main and cost measurements taken today. Anything worked out rather than measured is marked (inferred). Full list in the appendix.

2. Getting stable: priorities, in order

"I want a retro document first. I don't want more hacks." … "and priorities to get things stable right now. Number one."

Fede, 2026-10-01

Stability is number one. A red main stops merges, deploys and everyone's PRs at once, so nothing else pays off until it holds.

1. Main stays green

(a) Every test that can turn main red runs on the PR before it merges. That is the full bookkeeping set (tests that keep shared lists, like routes and fields, in sync) plus the safety checks. About 4 minutes in parallel, cents per push (inferred). Today the PR runs only the subset picked by which files changed: about 310 of 1,044 guard files. The queue and main ran the rest.

(b) No stale greens. A PR whose full checks ran on an old copy of main re-checks against current main before it merges.

(c) Machines don't die mid-run. Machines and deploy steps caused 23% of red stretches over 90 days (18% of red hours), and about 16% since Sep 13. An earlier 30-day sample said 55%, but it was skewed by the Sep 8–12 machine incident (see section 3). Infra reliability is part of keeping main green, not a cost question.

Evidence: today's breaks at 3:31 PM and about 4 PM. In the 4 PM break, three culprits never ran the failing test. The fourth had passed the full set two days earlier and merged with no re-check. The 3:31 PM culprit's test never ran on its PR either.

2. A red main is fixed fast, by one owner, within 30 minutes

We already have the one-driver rule: one session owns a red main, everyone else keeps working. Today main was red from 3:31 PM to at least 4:20 PM. Deploys stalled 47+ minutes with 119 changes waiting. About 37 open PRs showed red only because main was red.

3. Stop changing CI underneath the team

CI changes go out only in a set window, each after a trial run. 29 CI changes merged during the last queue attempt. The machine type flipped 3 times in 20 hours.

4. Then cost, then speed

Cost is not down yet: about $385/day measured at 1 PM, flat vs yesterday. The target is under $65.

One-machine trial. Since this morning, 1 in 4 PR pushes also runs all checks on one machine, silently, gating nothing. In 43 samples it finished in a median 6.8 min vs 17.6 min for today's multi-machine setup, faster in 40 of 43. Not proven yet: its list-test step failed in every sample, probably because main was red (inferred). It needs a clean re-check before any switch. Full comparison due 2026-10-02 around noon.

Open decision for Fede: should a red bookkeeping-only test on main block deploys?

A Keep blocking, as today.
B ★ Recommended. A red that is bookkeeping-only does not block deploys; it is fixed forward within 30 minutes. Safety and product test reds still block.

Why B: a stale list entry does not change what customers get (inferred), yet today it held 119 changes out of production. This is a rule change, not a code hack. It waits on Fede's yes.

3. Reducing reds: what 90 days of main says Proposed — pending review

Main was red for about 234 hours in the last 90 days, about 10% of the time, across 367 separate red stretches. Before the merge queue was retired on Jul 22 it was red about 1% of the time. After that it was red about 11%. Red stretches per day went from 0.4 to 3.4, then 7.6 in mid-September and 16.8 in the last four days.

Why main went redShare of red stretchesShare of red hoursWhat it means
The test that broke main never ran before merge46%57%The PR ran a subset of the tests. The one that broke only runs on main.
Machines and deploy steps23%18%Runner shutdowns mid-run and Vercel deploy errors
Stale green7%11%The PR passed days ago, main moved on, and it merged without re-testing
Live voice-agent settings changed11%5%Tests that read ElevenLabs's live settings. Main goes red with no code change.
Merged while red7%5%Admin merges, and a required check that does not check the code
Flaky6%4%Passed on the PR, failed on main, and no fix was needed

This is a class problem, not a few bad tests. It takes 73 different tests to cover 80% of the red hours. The repeat offenders are mostly bookkeeping lists that a new page or setting has to be added to: the sensor registry (16 times), the route manifest (11), eval model pins (8), the user route inventory (7), and the single-writer list (7).

Fixes, ranked by reds removed

FixRed stretches removed per monthRed hours removed per month
Run every test that can break main on the PR, against current main3532
Bookkeeping lists update themselves instead of failing the build1912
Machines that don't die mid-run (spot quota, guard pins on 4+ CPUs)259
Re-test a stale green before it merges88.5
Vercel deploy errors stop turning CI red35
Live voice-agent tests move off the blocking path and alert instead134
Close the merge-while-red path84
Quarantine flaky tests (Gera's audit)83

These are estimates that assume each fix is fully effective. They overlap, so don't add them up.

Recommended order.

  1. Run the full main-breaking set once per ready PR, against current main. This one fix covers the two biggest causes, which together are about two thirds of red hours. Cost estimate: about $67/day. Most of that can come back by no longer running the full suite on every main push, about $131/day today (estimate).
  2. Make the bookkeeping lists regenerate themselves.
  3. Take the live voice-agent tests off the merge and deploy path.
  4. Close the merge-while-red path.
  5. Fix runner reliability.

Flaky tests come from Gera's audit (test speed tracker). Nothing here is built yet, because CI changes are frozen until Fede and Gera pick the order.

Correction: an earlier version of this page said machines caused 55% of red main. That figure came from a 30-day sample dominated by the Sep 8–12 machine incident, which was fixed Sep 12. The full 90-day count says machines and deploy steps caused 23% of red stretches. Since Sep 13 the figure is about 16%.

Method: every red stretch from Jul 3 to Oct 1 was classified, with no sampling. The culprit is the PR behind the first red commit. "Never ran before merge" versus "stale green" was read from PR logs for 194 stretches. "Flaky" is inferred. Red hours include overnight gaps with no pushes, so overnight stretches count high. Data: scratchpad deep-ci/main (episodes, pareto, fixes, repeat offenders).

4. The five attempts

A merge queue is a GitHub feature that lines PRs up and tests each one combined with everything ahead of it before it lands. If a PR fails, it is kicked out and every PR behind it is retested without it.

WhenWhat we changedWhat happenedWhy it failed
1. Jul 14 – Jul 22
8 days
The queue became the main test gate. PRs ran a small slice of tests; the full suite ran only in the queue. One PR per batch was allowed. It never batched: 66 queue runs for 63 PRs in a day. A green PR waited for a second full run (4–13 min). Failures were flaky tests on two bad days (18 and 24 failures), each restarting everyone behind. About a quarter of the CI bill. Too little traffic to batch: PRs arrived 5–12 minutes apart, slower than the queue emptied. Its catches were flaky-test storms (inferred): 104 red in 615 runs, no one-off cross-PR catches found. Retired; the full suite moved to after merge.
2. Sep 13, 10:49–11:31 PM
42 min
"Take two": real batching (at least 2 PRs, 3-minute wait), full suite in the queue. CI ran and passed on the queue's test commits, but the checks GitHub requires never reported there, so no PR could pass. Four PRs sat about an hour. Plumbing: the queue's checks were not the same as the PR's required checks. Gera turned it off by hand.
3. Sep 13, 11:48 PM – 12:23 AM
35 min
Switched back on the same night. Same stall. The fix for the reporting merged about 80 minutes after it went off. Same cause. Gera removed it again; Fede ruled the next day that it stays off, and the code was reverted.
4. Sep 30, 5:17–6:38 PM
81 min
After the CI/CD design review: queue on, batches of 5, then 10, in the middle of a backlog. The first batch lost a cheap cloud machine that Amazon took back, so the whole batch failed and re-queued (about 45 min lost). 4 merges in the 5–6 PM hour. 97 PRs merged from 6:30 to 7:10 PM, almost all after it went off. One machine loss killed a batch of up to 10 PRs, at a time when we needed to catch up. Fede: "is the queue even worth having right now that we are trying to go faster and catch up".
5. Oct 1, 5:49 AM – 3:27 PM
9.6 hours
The new approach: only the fast checks in the queue (full suite after merge), every required check reports in the queue, full-price machines, batches raised 5 → 10 → 20. 39% of queue runs failed. Median 40 min in the queue, 1 in 10 waited over 80. Line grew from 47 to 72. Merges fell to about 15 an hour, down from about 24 overnight. A pile-up, detailed in the next box. Off on Fede's "We need emergency action." 22 PRs merged within 3 minutes.
Attempt 5 in detail (Oct 1): eight things went wrong in one day
  • Checks that only ran in the queue. The bookkeeping tests that keep shared lists in sync (routes, workflows, file lists) ran in full only in the queue. In a midday sample they caused 8 of 12 failed batches. A database-safety check failing on the combined code caused the other 4 (whether that check runs in full on PRs is not verified).
  • A failing PR re-queued with no fix. One PR failed the database-safety check, went back in with no new commit, and caused 9 of 11 failures in one stretch.
  • Cheap machines again. At 10:23 AM queue jobs moved back to cheap reclaimable machines to save money. From then, 9% of runs lost a machine, each adding about 12.6 minutes. Before, on full-price machines: 0 of 576 jobs lost.
  • Our own CI change. A CI change from this lane failed a script-safety check that ran only in the queue. It failed every batch it joined for about 40 minutes (from about 12:50 PM).
  • Main red for two hours. A test that depends on a warm cache kept main red from about 12:50 to 2:43 PM; deploys were held.
  • Line-jumping. Moving one PR to the front voided a wave of 9 nearly-green builds.
  • The fix flushed the line. Landing "stop at the first failure" (3:03 PM) required dropping the queue rule for under a minute. That silently emptied the queue and un-armed 70 PRs; 53 were re-armed by script.
  • Churn underneath. 29 CI changes merged while the queue was on. The queue's machine type flipped three times in 20 hours: cheap, full-price, cheap, full-price.

After "stop at the first failure" landed: 27 runs passed, 0 failed, 5 cancelled, in the 24 minutes before the queue went off. Too short to credit it alone; the broken CI change and the re-queued PR were already out by then (inferred).

Today, end to end: PR opened → merged median 73 min (1 in 10 over 9 hours); merged → live median 79 min.

The retros before this one

Two earlier write-ups each proposed a new approach. Both read the problem as "the queue is set up wrong," not "PRs arrive unready."

"July's queue ran one full suite per PR by construction … The new config batches 2–3 (up to 5) PRs per run after a ~3-minute wait, fixing the exact 'never batched' root cause."

"Merge queue, take two", ship-in-15-minutes page, Sep 13. It failed that night on a different cause: checks not reporting.

"Fix: test each PR against the latest main before it merges (a merge queue), then deploy that exact result with a small canary and automatic rollback."

CI/CD design review, Sep 30, "Decided: merge queue yes (after the backlog is caught up)".

The Sep 30 plan had the right order, and we skipped it. Its step 3 was "the bookkeeping tests always run on PRs, never skipped." Its step 5 was "merge queue on, about a week in shadow first." Instead, the full bookkeeping set was moved off PRs that same evening and the next morning. The queue went on the same afternoon, with no shadow week, during the backlog.

5. After the queue went off: the choke point moved to deploys

"It seems like the bottleneck moved to the deploy stage… I moved the merge queue and now the choke point is on the next step."

Fede, 2026-10-01

Lesson: the queue was hiding the same root cause. Without it, the failures land on main instead of in the queue. The place changed; the cause did not.

6. The common cause

The queue was always the first place some checks ran, and it was switched on live, with no trial week. In a queue, every failure is paid by everyone behind it. So anything that leaks into the queue gets multiplied: a check gap, a flaky test, a lost machine, a bad CI edit. Without a queue, the same thing costs one PR.

CandidateSeen inVerdict
Checks that run only in the queue1, 2, 3, 5root July: full suite only in the queue. Sep 13: required checks never reported. Oct 1: the bookkeeping tests, including the script-safety check.
High failure rate, with everyone behind restarting1, 4, 5the multiplier Turns any failure into lost hours for the whole line (see the math).
Our own CI changes while the queue was live4, 5root We debugged and rebuilt CI on the same line the team merges through.
Arrival rate vs capacity1 (too low), 5 (too high)flipped July: a PR every 5–12 minutes, nothing to batch. Now about 20 an hour, which leaves no slack for failures.
Cheap machines that get taken back4, 5trigger Killed attempt 4. On Oct 1, after the switch back, about 9% of runs lost a machine and ran about 12.6 min longer. They showed up as cancelled runs, not failures.
Main red5amplifier With a queue, a red main stops everyone, and the red-main fix path (drop the rule) flushed the line.
Agents re-queuing kicked PRs, line-jumping5amplifier One unfixed PR caused 9 of 11 failures in one stretch. One jump voided 9 builds.
Slow, heavy queue runs1, 5contributor About 12 min per run. The main build-and-typecheck job took 9 min in the queue vs 3.4 on a PR (an extra build and cold caches).

7. The math

GitHub builds the line as nested stacks: PR 1; PR 1+2; PR 1+2+3; and so on. If PR 3 fails, every stack from 3 up is thrown away and rebuilt. So the number of PRs that land per cycle is capped by how many pass in a row, not by how many builds we pay for.

PRs per hour ≈ (parallel builds ÷ run time) × (1 − work thrown away)
PRs landed per cycle ≈ (1−p)/p × (1 − (1−p)builds)   p = share of PRs kicked

On paper: 10 builds ÷ 12 min = 50 PRs an hour. With 1 in 7 PRs kicked (today's 14%), on average only about 6 pass in a row. Each 12-minute cycle lands about 5, so about 24 an hour, and doubling the builds to 20 only reaches about 29. That is why raising builds from 10 to 20 at 2:55 PM did not help.

PRs kicked (p)PRs/hour, 10 buildsPRs/hour, 20 buildsvs ~20–24/hour arriving
2%45812× headroom
3%42742× headroom
5%3861thin in bursts
14% (Oct 1)2429line grows
25%1415collapse

Run time 12 min. These are best-case ceilings (inferred): they ignore lost machines, line-jumps and a kicked PR's own rework, all of which happened. A line that clears barely faster than it fills grows without limit in any burst. The 39% figure is per queue run, not per PR. It means 4 in 10 runs produced nothing; a midday cost check found 57–65% of queue machine spend going to failed runs.

8. Were cross-PR collisions ever the real problem?

"Tests PRs against each other makes sense. But did we identify that as a common pain point / bottleneck in real ci runs? Did we sample last 30 days to see if that's really saving the issues."

Fede, 2026-10-01

Answer: clashes between PRs are real but a minority, about 1 in 6 red-main episodes. Most red main is machines, tests that never ran on the PR, or one bad PR. The queue does catch stale greens, but today it spent most of its runs on 5 bad PRs. This supports option B: close the PR-side gaps and add a stale-green re-check first.

A collision means two PRs that each pass alone but break main together. A stale green is the same thing over time: a PR passed on an old main and broke on today's. These are the only failures a queue catches that PR checks cannot. All numbers below are samples and partly (inferred).

SampleCollision or stale greenTest never ran on the PRFlaky testMachines and outside servicesOther
Red main, Sep 1–Oct 1: 958 red builds in 264 episodes (130 analysed)15%12%7%55%2% red on the PR and merged anyway; 10% unknown. Machines shut down mid-run in 54 episodes, the live voice agent changed in 8, deploy steps in 7 (this sample is skewed by the Sep 8–12 machine incident; the full 90-day count is 23% infra, see section 3)
Oct 1 queue, 9 AM–3:27 PM: 455 runs, 147 red19 runs——0 red128 red runs came from 5 bad PRs failing every batch they joined: two real-database test problems (46 and 44 runs), a marker check (18), our own CI change (12), a workflow pin (8). Lost machines showed up as 16 cancelled runs, not failures
Oct 1 main breaks after the queue went off (5 culprits)14——3:31 PM: a CI-settings change whose pinned test never ran on its PR. ~4 PM: 3 PRs that never ran the list tests, plus 1 stale green
Sep 30 review: the "25 of 34" failed main runs (one day)0——3 runs21 runs came from 2 PRs whose list test was already red on their own PR and merged anyway. 3 were the live voice agent changing; 1 untraced. These were runs, not causes
July queue: 615 runs, 104 red0—most (inferred)—The same test failed in up to 32 runs: flaky-test storms (inferred). No one-off catches found. The older count said 434 runs

What it means for the plan: machines and outside services are the largest share of red main, and machine shutdowns alone are the single largest cause. So infra reliability now sits under "main stays green" in section 2. A queue stays a maybe for later, not a fix for now.

9. What would have to be true for a queue to work here

ConditionNeededOct 1, measured
Same checks on the PR as in the queueNo check runs only in the queueThe full bookkeeping set ran only there
PRs kicked from the lineUnder 3% (about 2× headroom at 10 builds)14%
Queue runs failingUnder 5%39%
One queue run10 min or less, stopping at the first failureAbout 12 min; stop-early only from 3:03 PM
Machines lost mid-runUnder 1% of runs9% on cheap machines; 0% on full-price
Main green95%+ of the workday; red-main fixes land without touching the queue ruleRed about 2 hours; the rule drop flushed 70 PRs
CI changes while the queue is onNone outside a set window, each tried in a trial run first29 in under 10 hours
Agent behaviorA kicked PR re-enters only with a new commit; line-jumps only for red-main fixesBoth broken
Trial firstOne week measuring all of the above with nothing waiting on itNone of the five attempts had one

10. The alternatives

OptionWhat it buysWhat it costs
1. No queue (today): merge on green, heavy tests after merge, automatic revert of a single culprit, deploys held while main is red Merges never wait. Matches Gera's priority: "I'm not urgent for it to show in production, but I am urgent to land the code." Main goes red whenever the PR ran fewer checks than main. 4 minutes after the queue went off, a PR that changed CI machine settings merged on green and broke main: a pinned test the PR never ran. Overnight before the last attempt, 172 of 187 main runs failed. Gera's own flaw: "Bad code reaches main. We're all gonna pull it."
2. Require up-to-date branches, no queue Every PR is tested on the latest main. Catches collisions exactly. Main moves every ~3 minutes; a PR's checks take ~11. PRs never catch up. Measured in August at about 30 merges a day, a fraction of today's 400–500: 39% of all commits were catch-up syncs, about 44 hours of re-testing unchanged code in two days, one PR synced 15 times.
3. Queue with small batches, or "head-only" checking (only the last stack in a batch must pass) Smaller blast radius per failure; fewer runs. Does not fix the failure rate. At 14% kicked, batches of 4 clear about 14 PRs an hour, below arrivals (inferred). Head-only lets a batch land on one result, so when it fails, finding the culprit costs more. Not tried here.
4. Merge train with automatic bisect and revert: merge on green, test main every few minutes, find the culprit and revert it Merges never wait; heavy tests run once per train. Most parts exist: the after-merge lane, single-culprit revert, the deploy hold. Main is red between a bad merge and its revert. A flaky test causes wrong reverts. Whether reverts happen at all is still an open question to Fede. This is not the Zillow behavior Fede described ("you just get kicked out of the queue"): that is fail-fast inside a queue.
5. Run the queue's full check set on the PR, so a queue (if any) only re-checks Removes the biggest failure class from both worlds. It would have caught Oct 1's queue-only failures before they entered the line, and the 3:31 PM break after it. A slightly longer PR lane: the bookkeeping set runs as 6 parallel ~4-min pieces, alongside checks that already take 3–9 min. About 4 cents a push on cheap machines (inferred). Does not catch true collisions.
6. Gera's idea: own tests first, then a capped queue. "Does the PR pass its own section's tests; if so, add to merge queue… limit it to 5 PRs at a time, every 10 minutes." A steady, predictable pace. Small batches limit the damage per failure. Only PRs that passed their own tests enter. Works only when fewer than about 3 in 100 PRs get kicked. At today's 1 in 7, a 5-PR batch passes about half the time (0.865 ≈ 0.47) and clears about 15–20 an hour, below the 20–24 arriving. Under 3%, it clears about 25–28 an hour. "Its own section's tests" is exactly today's gap: the section tests miss the list tests. One bad PR delays four good ones by 10+ minutes, plus the time to find which one.

11. Recommendation Proposed — pending review

A Leave the queue off for good and keep today's setup (option 1) unchanged.
B ★ Recommended: stable first. Queue stays off. Work in the order of section 2. (1) Main stays green: every check that can turn main red runs on the PR (option 5), a stale green re-checks against current main before it merges, and machines stop dying mid-run. (2) A red main has one owner and is fixed within 30 minutes. (3) CI changes go out only in a set window, each after a trial run. (4) Then cost and speed, starting with the one-machine trial once it passes on a green main. (5) Bring a queue back only if a week of measuring meets every threshold in section 8, and only if the collision count says it is worth it.
C Turn the queue back on now with today's fixes (stop at first failure, full-price machines, the pre-queue check).
D Require up-to-date branches instead (option 2).
E Build a merge train with automatic bisect and revert (option 4) instead of a queue.

Why B: it puts stability first and fixes the cause shared by all five attempts and both of today's main breaks. None of it needs a queue, and none of it is a hack. Gera's capped queue (option 6) only works after step 1 brings kicks under 3 in 100. C repeats attempt 5 at a 14% kick rate. D was measured as a treadmill in August at a fraction of today's volume. E keeps main red between a bad merge and its revert, which is the thing Gera flagged.

12. Engineer appendix

Ruleset history, PRs, run ids, and sources

Ruleset 14925316 ("Require CI"), merge_queue rule, from the GitHub ruleset history API

VersionTime (CT)ActorState
43073673Jul 14 12:13 PMfede-propflowON: ALLGREEN, build 5, merge 5, min 1, wait 5, timeout 30
43115357–43610155Jul 14–19bothtimeout 15/30/45, wait 5→10
44072984Jul 22 1:15 AMgera-propflowOFF
49589307Sep 13 10:49 PMfede-propflowON: ALLGREEN, build 5, merge 5, min 2, wait 3, timeout 60
49591082Sep 13 11:31 PMgera-propflowOFF
49591753Sep 13 11:48 PMfede-propflowON (same settings)
49593303Sep 14 12:23 AMgera-propflowOFF
51497955Sep 30 5:17 PMfede-propflowON: build 5, merge 5, min 1, wait 5, timeout 90
51498771 / 51498782Sep 30 5:27:49 / 5:28:03 PMfede-propflow14-second OFF/ON (admin merge, inferred)
51501821Sep 30 6:17 PMfede-propflowbuild/merge 10, wait 3
51502749Sep 30 6:34 PMfede-propflowbuild/merge 5
51502913Sep 30 6:38 PMfede-propflowOFF
51556813Oct 1 5:49 AMfede-propflowON: build 5, merge 5, min 1, wait 2, timeout 30
51566658Oct 1 7:20 AMfede-propflowbuild/merge 10
51619163Oct 1 2:55 PMfede-propflowbuild 20, merge 10
51620073 / 51620082Oct 1 3:03:15 / 3:03:21 PMfede-propflow6-second OFF/ON to admin-merge #14934; silently flushed the queue
51622689Oct 1 3:27 PMfede-propflowOFF

strict_required_status_checks_policy is false in every version from Jul 3 on. The August "strict: true" reading on the delivery page came from classic branch protection, not this ruleset (inferred).

PRs by attempt

  • 1 (July): #3694, #3747 (review / Nested Gate report on merge_group), #3732 (queue becomes the authoritative gate, capped affected), #3752 (~5-min queue, 12 shards), #3767 (20 shards), #4049 (group-diff selection), #4130 (stop re-validating main on push), #4139. Retired by #4303 / ADR-0107 (docs/adr/0107-deploy-gate-relocation-retire-merge-queue.md), follow-up #4444.
  • 2–3 (Sep 13): #8354 (full suite on merge_group), #8363 (auto-merge freeze on red main; kept), #8377/#8379 (smoke tests), #8385 (mint the seven required contexts on a merge-group head; merged 1:46 AM CT Sep 14, after the second removal). Measured problem in #8385: run 34803923258 on 150caf5f04 concluded success but none of the required contexts were posted. Reverted by #8485 (Fede 2026-09-14).
  • 4 (Sep 30): #14440 (core lane on merge_group), #14455, #14491 (full guard set and test-full main-only). First batch run 36786927853 lost "Unit Tests (full 1/2)" to a spot reclaim (exit 137) → #14477 (merge_group on-demand). Fede's words, CI lane transcript 6:37 PM CT: "is the queue even worth having right now…", "you are blocking my entire productivity", "and my teams".
  • 5 (Oct 1): #14696 (PR guard pins = fence only), #14705 (queue runs the fast lane only), #14755 (guard pins 6 shards), #14765 (every required check reports on merge_group), #14845 (sidecar + marker checks block on PRs), #14863 (queue back on spot, 10:23 AM), #14934 (fail-fast, 3:03 PM), #14948 (pre-enqueue check), #14950 (warm caches), #15019 (CI Checks + affected tests on-demand in the queue, merged after OFF). Failing-batch causes: #14744 (user-route-inventory drift), #14848 (check:ddb-escapes, re-enqueued without a new push), #14949 (shell-pipefail ratchet, ~12:50–1:30 PM CT). Line-jump of #14972 at 2:17 PM CT voided 9 green builds.
  • After OFF: 3:31 PM CT, a PR that changed runs-on labels in ci.yml merged on green PR checks and broke main: src/__tests__/ci-cost-routing.test.ts was stale, and the PR lane runs affected tests only. The fix was folded into another PR. ~4 PM CT: second break in the route-inventory and legacy-field list tests (three culprits path-selected out of the guard set, one stale green whose full guard run was two days old). Deploys held from 3:28 PM CT; factory dashboard 4:17 PM CT "On main 55, Deploy batch 54"; 119 changes waiting, ~37 open PRs red from main's red.

Measurements

  • 9:00 AM–2:15 PM CT: 333 merge_group runs, 38.8% failed; time in queue median 40.5 min, p90 80.2 (n=91); kicked 14%. After fail-fast (3:03–3:27 PM): 27 success, 0 failed, 5 cancelled.
  • Spot report (spot-int/report.md, 9:04 AM–2:11 PM CT): on-demand era 576 critical-job executions, 0 interruptions; spot era 2,222, 30 interruptions; 24 of 256 runs (9.4%) affected, +12.6 min median.
  • Earlier window (5:49–11:40 AM CT): 286 batch runs, time in queue 28.7 min median / 51.9 p90, run 12.4 min, slot wait ~13 min; CI Checks 9.0 min in batch vs 3.4 on PR. 38% batches failed (8/12 guard-pin drift, 4/12 DDB escape gate); 62% of PRs kicked at least once.
  • 11:38 AM CT cost pass: 57–65% of queue spend on failed runs; queue ~63 runs/hour.
  • Merges per hour, Oct 1 (GitHub search, merged-at, UTC hours): 00–09Z avg ~24/h; 11–19Z (queue on) avg ~15/h; 20Z 86. 488 merged on Oct 1; 398 on Sep 30. July 16–20: 319 merged (~64/day).
  • Main CI before the Oct 1 queue: 172 of 187 runs failed; after: 6 failed / 7 passed / 12 cancelled by 9:46 AM CT (CI/CD page).
  • PR lane guard coverage: path-selected, ~310 of 1,044 guard files. CI cost ~$385/day at 1 PM CT Oct 1, flat vs Sep 30 (target < $65).
  • One-machine shadow trial (1 in 4 PR pushes, non-gating): n=43, median 6.8 min vs 17.6 min multi-runner, faster in 40/43; its guard-list step failed in 43/43 (main red, inferred). Full comparison due 2026-10-02 ~noon CT.
  • Gera's capped queue: batch pass rate (1−p)5, at p = 0.14 ≈ 0.47; 6 cycles/hour cap = 30 PRs/hour.
  • Collision sample (coordinator, Oct 1): red main Sep 1–Oct 1, 958 red builds → 264 episodes, 130 analysed: 15% green-alone/red-combined, 12% test not run on PR, 7% flaky, 55% infra/external (54 spot/runner shutdowns, 8 live ElevenLabs agent drift, 7 deploy steps), 2% red on PR and merged, 10% unknown. Sep 30 "25 of 34": 21 from 2 PRs merged with the list test red on the PR, 3 ElevenLabs drift, 1 untraced, 0 green-on-PR. July re-measured: 615 merge_group runs, 104 red, one test failing in up to 32. Oct 1 queue 9 AM–3:27 PM CT: 455 runs, 147 red, 128 from 5 PRs (46, 44, 18, 12, 8), 19 collision/stale-green, 0 red from lost machines (16 cancelled).
  • Throughput model: E = (1−p)(1−(1−p)c)/p PRs per cycle, cycle = 12 min, p = share of PRs kicked, c = max_entries_to_build. Assumes each failure costs one cycle and nothing else.

Sources

  • gh api repos/PropFlow-Technologies/propflowai/rulesets/14925316/history and each /history/<version>.
  • git log -S merge_group on origin/main; docs/runbooks/ci-and-deploy.md (pre-enqueue paragraph); ADR-0107.
  • ~/.claude/logs/ci-decisions.log (Sep 30 night to Oct 1, 3:36 PM CT).
  • Docs pages: ci-cd-architecture-2026-09-30 (sections 3, 6, 7, 8, "Where the minutes go"), ship-in-15-minutes-2026-09 (section 17), pipeline-delivery (August BEHIND treadmill), lead-time-top-moves, ci-factory, always-shipping-2026-09.
  • Standup transcript 2026-10-01 (raw): Gera on bottleneck placement and post-merge testing; Fede on the Zillow kick-out.
  • CI lane transcript (agents-004, session 33c962ee) for the Sep 30 quotes.